MALENY STATE HIGH SCHOOL HALL REFURBISHMENT
Project Details
Duration:
8 weeks construction
Size:
500m²
Completed:
2020
Location:
50 Bunya Steet, Maleny
Work:
Construction by Future Fitouts
Project Overview
Contracted to deliver another of Ridgemill’s designs for Maleny SHS;
Works involved the construction of structural sports flooring, line markings and fixtures for Maleny Hall, as well as bathroom demolitions and refurbishment works.
KEY LEARNINGS
Working in a live environment, during school term for the majority of the works in an around students, teachers and other staff. The challenge of blocking off the school hall daily to ensure no footprints were left on the newly laid floor during the curing period.