RAY WHITE NEW OFFICE FITOUT REDCLIFFE

Duration:

6 weeks construction

Size

399m²

Completed:

2022

Building Class:

Class 6

Location:

Redcliffe

Work:

Design & Construct by Future Fitouts

Project Overview

Contracted by Ray White Redcliffe to design and fitout their recently acquired building which suffered severe damage by the January floods.Future Fitouts designed, managed, and coordinated all contractors including; demolition works, painting, vinyl and carpet flooring throughout, amenities refurbishment, and various joinery throughout including two kitchenettes and a stone reception desk.

The brief was to create a moody yet classy space taking into consideration the minimal natural light the building had. Walnut timber grains, terrazzo-look vinyl, textured light grey tiles and the restoration of VJ panels gave the building a new life.

The new office space was handed over on time and on budget to the very excited Ray White team.