THE HAMILTON LEVEL 2 DEFIT & MAKE GOOD

Hamilton Level 2 De Fit & Make Good.

Project Details

Duration:

4 weeks construction

Size: 

280 m2 approx.

Completed:

2020

Work:

Design & Construct by Future Fitouts

Location:

L2 Commercial Tower, 33 Remora Road, HAMILTON

Project Overview

Contracted by the Shayher Group for a full defit and make good of the back to base build plan of current display suites and offices. The Project also included assorted building works including the construction of new tenancy walls, new ceilings and split electrical and mechanical services from the adjacent tenancy.

Methodology

The Future Fitouts team completed the project on time while working to minimise disruption to other building tenants as well as working alongside another contractor undertaking a fitout on the same floor. Key methodologies included the removal of all display suite materials to be utilised as spares in a separate building.